Hierarchy,Identification,Name,ScheduleStart,ScheduleFinish,ScheduleDuration,ActualStart,ActualFinish,ActualDuration,Relationships 1,0,Construct Bridge,,,,,,, 2,1,Stage 1 - Set girders in place,,,,,,,0FS1 3,1.1,Construct piers and abutments,,,,,,,1FS11 3,1.2,Install elastomeric bearing pads,,,,,,,11FS12 3,1.3,Set and brace girders,,,,,,,12FS13 3,1.4,Remove temporary strands,,,,,,,13FS14 4,1.4.1,Remove polystyrene,,,,,,,14FS141 4,1.4.2,Cut strands,,,,,,,141FS142 4,1.4.3,Fill blockouts,,,,,,,142FS143 2,2,Stage 2 - Cast diaphragms and place bridge deck reinforcement,,,,,,,1FS2 3,2.1,Install temporary bracing,,,,,,,2FS21 3,2.2,Construct deck,,,,,,,21FS22 2,3,Stage 3 - Cast bridge deck,,,,,,,2FS3 2,4,Stage 4 - Cast traffic barriers,,,,,,,3FS4