Assistance with Work Schedules-Task ICOM

I am using BB version 240602 and want to add a Work Schedule to my IFC model and came across the following.
Could somebody please explain how an demolish element would be added in the “Task ICOM” option would it fall under “Inputs” or “Outputs”?
Thanks in advance

Tagged:

Comments

  • Hi @Roel

    I am using BB version 240602 and want to add a Work Schedule to my IFC model and came across the following.
    Could somebody please explain how an demolish element would be added in the “Task ICOM” option would it fall under “Inputs” or “Outputs”?
    Thanks in advance

    nice WBS!
    I'd be interested to know the use of "Inputs" in the UI, since I couln't figure out how to load materials onto the schedule I didn't explore 4D feature in BBIM too much, do you know anything about it? cheers

  • Hi @steverugi
    I would like to figure the whole "4D" feature out and then move to "5D" all I know is I need to learn more... Imported the WBS from Excel to MS Project to BBIM.
    Cheers

  • @Roel said:
    Hi @steverugi
    I would like to figure the whole "4D" feature out and then move to "5D" all I know is I need to learn more... Imported the WBS from Excel to MS Project to BBIM.
    Cheers

    the UI is not the most recent but I learned a bit from here
    YTvideo

    feel free to ask if you need assistance with 5D

    emiliotassoRoel