BlenderBIM Add-on: Construction Scheduling

Hi
In the Construction Scheduling tab, I created Work Calendars. I added a weekly time schedule for Monday, Tuesday, Wednesday, Thursday, and Friday.

I started adding a few tasks and created a timeline for the tasks:

Schedule Start: 01.05.2024
Schedule Finish: 08.05.2024
Schedule Duration: 8 days

The duration is shown as 8 days, but the correct duration should be 6 days because my working week excludes weekends (i.e., Saturday and Sunday). This means two days should be subtracted from the 8 days, but this adjustment has not happened. Can anyone help me? I want to know the solution for calculating the duration without weekends. Is this duration correct, or is there a programming problem or an unknown solution?

Comments

  • edited May 2024

    @MahdiA2024 said:
    Hi
    In the Construction Scheduling tab, I created Work Calendars. I added a weekly time schedule for Monday, Tuesday, Wednesday, Thursday, and Friday.

    I started adding a few tasks and created a timeline for the tasks:

    Schedule Start: 01.05.2024
    Schedule Finish: 08.05.2024
    Schedule Duration: 8 days

    The duration is shown as 8 days, but the correct duration should be 6 days because my working week excludes weekends (i.e., Saturday and Sunday). This means two days should be subtracted from the 8 days, but this adjustment has not happened. Can anyone help me? I want to know the solution for calculating the duration without weekends. Is this duration correct, or is there a programming problem or an unknown solution?

    make sure the calendar is properly stored

    and assigned to the work schedule by clicking on the grid symbol

    as you can see my end date is as expected (10/5/24)

    MahdiA2024
  • @steverugi
    Thank you for help

Sign In or Register to comment.