Bonsai - Task duration
If it is possible, how do I set the duration on a task to anything less than an hour?
I am also unable to delete the duration on tasks. It keeps coming back when I click on other tasks. I have tried setting it to 0 and also deleting it. Seems to work until I click on another task.
Thanks in advance.
Tagged:
Comments
Durations under an hour is not yet supported. I think calculation is still day based right now.
@aualby
Yes, it doesn't seem to like 0 duration, even if the task has IsMilestone checked, it reverts to previous settings.
Would you like to post an Issue here ?
Maybe there is a particular reason why it does it.
Thanks
All good, just worked out that what I was looking for was further down the screen. All working now, thank you.
Ok thanks. I can enter them, I gather the calculations are not cumulative except for Days or greater.